CONSTRUCTION MANAGEMENT PLAN

In September 2022, Native Land received planning permission for proposals to refurbish and extend 105 Judd St to provide space that meets the needs of modern businesses and benefits to the local community.

J Coffey construction has been undertaking soft strip works on site, and demolition work has now commenced. J Coffey’s construction work will be carried out in accordance with a Construction Management plan, outlining how they will ensure that the construction works are managed safely and to the highest standards, minimising noise and disruption to neighbours.

Click here to view a copy of J Coffey’s Construction Management Plan.

The next stage of the works, commencing in September 2025, will be undertaken by McLaughlin and Harvey, including façade works, partial fit-out, mechanical, electrical and plumbing works, and new lifts.  The McLaughlin and Harvey team has prepared its own draft Construction Management Plan. for its upcoming works.

Click here to view a copy of McLaughlin and Harvey’s draft Construction Management Plan.

COMMUNITY LIAISON GROUP

The 105 Judd Street Community Liaison Group (CLG) meets regularly during periods when work is underway on site. The CLG provides a forum where the project team and local residents meet to share updates on construction work. The next CLG meeting will take place on 27 January 2025, 6pm-7pm on Zoom. Click here to register for this meeting.

Outline construction programme

August-October 2023

Site set-up and strip-out

September 2024

Demolition and basement works start

February / March 2025

Structural works commence

October 2025

Completion of structural works

Late 2026

Overall project completion

THE BRIEF FOR A LIFE-SCIENCES BUILDING

Working hours

We are proposing that construction works will only take place during the following days and times. These will need to be agreed by Camden Council following this consultation of the CMP but reflect the Council’s guidelines for construction working hours:

Monday to Friday: 8am – 6pm

There will be no works taking place on Sundays or public holidays

There may be a requirement for work outside these hours, including Saturdays, for activities such as:

  • Tower crane erection/dismantling works,
  • Mechanical Plant delivery,
  • Utilities / Statutory Connections,
  • Services shut down and emergency repairs.

Should the need for these works arise, we will ensure that we get in touch to let you know in advance.

Noise and dust

Dust and vibration monitors have been installed, providing real-time monitoring with alerts sent to the project team if agreed levels have been breached. When an alert is received the works will cease and the situation/ methods reviewed and adapted before continuing. Modern well-maintained machinery and tools will be used for all demolition works to minimise noise and vibration. Air Quality Monitors have been installed and will be maintained throughout the construction phase.

The main contractor on site, J Coffey, can be contacted using the details below:

Emailing us at 105JuddStreet@jcoffey.com

Calling us at 020 8426 4944

Visit our website www.jcoffey.com